Pension Committee |
|
Date of meeting: |
21 November 2024 |
By: |
Chief Finance Officer |
Title: |
Quarterly Budget Report |
Purpose:
|
This report provides the Quarter 2 forecasted financial outturn of the ESPF for the 2024/25 financial year |
RECOMMENDATIONS
The Pension Committee is recommended to note the report.
1. Background
1.1 The East Sussex Pension Fund’s (the Fund) business plan and budget sets out the direction of travel, objectives and targets to be achieved in the financial management for the administering authority to carry out its statutory duties in a structured way. The Pension Committee is charged with meeting the duties of the Council as the administering authority in respect of the Fund.
1.2 At its meeting on the 8 February 2024 the Pension Committee agreed a budget of £4.561m to support the business plan for 2024/25. The budget estimates do not incorporate any provision for investment fees earned by the investment managers since there is limited scope for the Fund influence these costs. This is due to the nature of the fees being based on factors outside the control of the Fund such as market movements, strategic asset allocation changes and ownership of mandates at pool level.
2. 2024/25 Quarter 2 Forecast Outturn Position
2.2 Regarding Investment Consultant costs, a procurement process is currently taking place with a new contract due to start in February 2025, a contingency of £50,000 was added to the budget as cost for this new contract are unknown. Due to restricted investment activity taking place after the strategy day and awaiting the outcome of the procurement, it has been assessed that it is unlikely for this to be needed and a general reduction due to reduced activity has resulted in a £68,000 reduction. There was also a piece of work around scenario analysis which was initially budgeted for at £25,000 but this will not take place this year bringing the forecast down by a total of £93,000.
2.3 There is a reduction to our estimated legal costs due the progress of the private credit mandates within ACCESS, this was put in as a contingency in case we needed to go outside of the ACCESS pool to procure private credit managers along with a reduction in other activity. This has resulted in a saving of £28,000.
2.4 When the budget was set there were a few items from the East Sussex County Council recharge that were included within the overheads line that should have been included in other areas of the budget. The Fund are now able to identify these costs more clearly and to record them against the appropriate expenditure line. £57,000 has been moved to administrative operational support services and £35,000 to improvement projects. After offsetting these line variances there is a £65,000 reduction to expected overhead costs. This due to the budget being set at a 15.7% overhead recharge rate, compared to the actual overhead recharge rate being 14.4%. Overheads are calculated based on a percentage of the Fund’s staffing costs.
2.5 There is an increase in the consultancy line for a one off cost of £25,000 that relates to the ongoing work around the GMP project that was not known at budget setting. It is not anticipated that there will be any additional charges for this work.
2.6 The 2024/25 outturn against budget line items is shown in the table below.
2024/25 Outturn Report
Outrun 2023/24 |
Item |
2024/25 |
2024/25 |
2024/25 |
2024/25 |
Budget |
Actual YTD |
Forecast Outturn Q2 |
Variance |
||
£'000 |
£000 |
£000 |
£'000 |
||
|
Fund Staff Costs |
|
|
|
|
1,958 |
Fund Officers |
2,436 |
524 |
2,464 |
(28) |
1,958 |
Sub Total |
2,436 |
524 |
2,464 |
(28) |
|
Oversight and Governance Expenses |
|
|
|
|
365 |
Investment Advice |
448 |
211 |
355 |
93 |
39 |
Actuarial Fund Work |
51 |
12 |
43 |
8 |
118 |
Actuarial Employer Work |
89 |
41 |
92 |
(3) |
(119) |
Employer reimbursement |
(89) |
(23) |
(92) |
3 |
38 |
Legal Fees |
57 |
5 |
29 |
28 |
42 |
Governance consultancy costs |
60 |
10 |
50 |
10 |
115 |
Audit |
120 |
(96) |
126 |
(6) |
598 |
Sub Total |
736 |
160 |
603 |
133 |
|
Investment Expenses |
|
|
|
|
107 |
Custodian |
100 |
(24) |
101 |
(1) |
107 |
Sub Total |
100 |
(24) |
101 |
(1) |
|
Administration Expenses |
|
|
|
|
489 |
IT Systems licenses costs and Hardware |
487 |
361 |
487 |
- |
315 |
Overheads |
531 |
79 |
374 |
157 |
246 |
Admin operational support services |
18 |
28 |
75 |
(57) |
106 |
Improvement projects |
87 |
35 |
122 |
(35) |
61 |
Consultancy |
20 |
14 |
45 |
(25) |
60 |
Communications |
37 |
- |
37 |
- |
26 |
Training |
33 |
6 |
21 |
12 |
84 |
Subscriptions |
80 |
23 |
75 |
5 |
53 |
Other Expenses |
11 |
3 |
11 |
- |
1,440 |
Sub Total |
1,304 |
549 |
1,247 |
57 |
|
Income |
|
|
|
|
(21) |
Other Income |
(15) |
(13) |
(15) |
- |
(21) |
Sub Total |
(15) |
(13) |
(15) |
- |
4,082 |
Total |
4,561 |
1,196 |
4,400 |
161 |
3. Conclusion and reasons for recommendation
3.1 The Pension Committee is recommended to note the second quarter projected 2024/25 outturn position.
Ian Gutsell
Chief Finance Officer
Contact Officer:
Russell Wood, Pensions Manager: Investments and Accounting
Email: Russell.wood@eastsussex.gov.uk